Attribution: Unknown (The wishing-tree on Isle Maree, Loch Maree)

Stacking Peat

01 Stacking Peat
02 Stacking Peat

Attribution: unknown

Construction of water storage tank at Inverasdale

We were very pleased to receive photographs showing the complete process of the construction of the water storage tank.  We have collated them into the photograph album.  

Click on photo album to view thumbnails and then click thumbnail to see the full size images 
Wester Lochewe » Wester Lochewe Work » Wester Lochewe Water Storage
01 Access Track Before Works
01 Access Track Before Works
02 Existing Water Storage Tank
02 Existing Water Storage Tank
Existing water storage tank serving Inverasdale.
03 Construction of Tank Cracking Formwork
03 Construction of Tank Cracking Formwork
Construction of tank - "cracking" formwork from newly cast wall.
04 Construction of Tank Placing Concrete
04 Construction of Tank Placing Concrete
Construction of tank - placing concrete on roof. Note reversed bucket on machine and concrete vibrator.
05 John O'Donovan Site Engineer
05 John O'Donovan Site Engineer
Site engineer, John O'Donovan, inspecting concrete finish.
06 Inside Newly Constructed Tank
06 Inside Newly Constructed Tank
Inside newly constructed tank as internal works approach completion.
07 Construction Brick Chamber
07 Construction Brick Chamber
Construction of brick chamber close to tank. Improved access track in mid-ground. Loch Ewe in background.
08 Helicopter Transporting Materials
08 Helicopter Transporting Materials
Helicopter transporting materials to reconstruction of river intake.
09 Hector Macdonald Site Agent in Helicopter
09 Hector Macdonald Site Agent in Helicopter
Site agent, Hector Macdonald, in the helicopter.
10 Laying Geotextile Material
10 Laying Geotextile Material
Laying geotextile material prior to placement of imported stone for extension to access track at tank site. Completed tank in background, now with earth surround.
11 High Pressure Polyethylene Pipelines
11 High Pressure Polyethylene Pipelines
Construction of high pressure polyethylene pipelines between storage tank and site of treatment plant.
12 Pipeline Crossing Stream
12 Pipeline Crossing Stream
Pipeline crossing of stream, with high pressure polyethylene pipes laid in ductile iron pipes (acting as protective ducts).
13 Constructing Pipeline Between Tank and River Intake
13 Constructing Pipeline Between Tank and River Intake
Constructing new high pressure polyethylene pipeline between new tank (mid-ground) and river intake.
14 Improved River Intake
14 Improved River Intake
Improved river intake. Note boggy conditions which necessitated delivery of construction materials by helicopter.
15 Improved Access Track and Storage Tank
15 Improved Access Track and Storage Tank
Looking at completed access track and storage tank. Site agent for R J Macleod, Hector Macdonald (yellow jacket), is talking to NoSWA clerk of works, Tony Kerrigan.

Poolewe Primary School Project

RCHS have been donated material which would appear to be a project by pupils of Poolewe Primary School and, although written some years ago, is worth reproducing as it gives insight into the activities of a small Highland primary.

The Playground

Attribution: unknown

Please submit your comment

Do you have any more information about any of the content on this page.

Your comments are always welcome: